Within how many days must a Claim of Lien be filed with the County Clerk after completion of work?

  1. 15 days

  2. 30 days

  3. 60 days

  4. 90 days

The correct answer is: 90 days

A Claim of Lien must be filed with the County Clerk within 90 days after the completion of work. This timeframe is established under Florida's lien laws, specifically designed to protect the rights of those who have supplied labor, materials, or services in a construction project. By filing within this 90-day period, a claimant preserves their right to enforce the lien on the property, ensuring a legal claim can later be made for payment if necessary. This extended period allows for any potential disputes or complications in determining the project's completion date, giving contractors and subcontractors ample time to assess their rights before proceeding with a lien. Understanding this timeframe is crucial for anyone involved in construction or real estate in Florida, as missing the deadline can lead to forfeiture of lien rights.