Building Code Administrators and Inspectors Florida Principle and Practice Licensure Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Building Code Administrators and Inspectors Florida Principle and Practice Licensure Exam. Prepare with detailed insights and exam tips. Ensure success in your licensure exam!

Practice this question and more.


If an owner fails to file a Notice of Commencement on a project with a total cost of $10,000, what will the contractor initially be unable to obtain?

  1. Approval of Building Inspections

  2. Certificate of completion

  3. Final payment from the owner

  4. Final Certificate of Occupancy

The correct answer is: Approval of Building Inspections

When an owner does not file a Notice of Commencement for a project, it creates complications for the contractor, particularly regarding compliance with local building codes and regulations. The Notice of Commencement is a critical document that notifies relevant authorities and parties about the commencement of a construction project, including details about the project’s scope, duration, and financial commitments. Because the Notice of Commencement is necessary for the contractor to legally proceed with the work and to request inspections, the initial inability to obtain necessary approvals for the building inspections arises. Without this approval, the contractor cannot affirm that the construction aligns with safety standards and building codes, potentially leading to project delays and complications. The process of obtaining building inspections is vital to ensure that each phase of construction adheres to the approved plans and meets safety requirements. Therefore, without the Notice of Commencement, the contractor's ability to secure these inspections is directly affected.