How many days after the final furnishing of labor, services, or materials can a claim of lien be recorded?

  1. 30

  2. 45

  3. 60

  4. 90

The correct answer is: 90

A claim of lien must be recorded within 90 days after the final furnishing of labor, services, or materials to a property. This time frame is stipulated in the Florida Construction Lien Law, which is designed to protect the rights of contractors, subcontractors, and suppliers by allowing them to secure payment related to the work performed. The 90-day limit ensures that any parties involved in the construction process must act promptly to protect their interests. This duration is crucial as it provides a clear timeline for all parties, allowing those who may have provided goods or services to enforce their rights without unnecessary delays. If a claim of lien is not recorded within this period, the right to establish a lien on the property is forfeited. Understanding this timeframe is vital for anyone involved in construction projects in Florida to safeguard their financial interests effectively.