Building Code Administrators and Inspectors Florida Principle and Practice Licensure Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Building Code Administrators and Inspectors Florida Principle and Practice Licensure Exam. Prepare with detailed insights and exam tips. Ensure success in your licensure exam!

Practice this question and more.


After how many days may a project be presumed abandoned if the contractor terminates the project without just cause?

  1. 30

  2. 60

  3. 90

  4. None of the above

The correct answer is: 90

The answer is based on how construction projects are monitored for progress and the implications of a contractor abandoning a job. In Florida, if a contractor halts work on a project without just cause, there is a statutory timeframe that determines when the project can be considered abandoned. This timeframe is critical for ensuring that property owners have recourse to address delays and to potentially seek other contractors to complete the work. A project is presumed abandoned after 90 days of inactivity, as this timeframe provides ample opportunity for the contractor to resume work or communicate any legitimate reasons for delays. This protection is in place to support both the interests of clients and the integrity of the construction industry, ensuring that projects do not remain in limbo indefinitely. Thus, the 90-day period serves as a clear and enforceable standard for assessing the abandonment of construction projects.